Sampson-Hoffland Update Number 4

It has been awhile since my last update and our new science building continues to be ahead of schedule. Faculty move in is scheduled for the first weeks in July. The interior of the structure is taking shape as flooring, paint,and lab furnishings are in place on 2nd and 3rd floors. All voice and data wiring is in place with trim out of jacks etc 90% complete. The voice and fiber backbones are in and tested. All network switches are on campus with a turn up date of May 12 expected for 2nd and 3rd floors. In discussion with Bob Erickson AV wiring will begin the first week of July. Building exterior excavation is to begin the week of May 5th weather permitting.