Main HVAC Update

From Facilities:

This week work will be happening in the last two offices on ground floor south west side, the Print Shop, layout in the LIS area on ground floor north, 2nd floor north hallway, and insulating for the tower piping. There may also be some piping on ground floor south that will be continuing toward the north and some work on replacement lighting in the Financial Aid Office area.