Sampson-Hoffland Building Update

This week was short due to Hollidays but a lot was accomplished. CEC (our wiring contractors) pulled the backbone voice and fiber from the new building to Union for voice and fiber to Main. As a cost savings we also pulled in the voice backbone for the eventual remodel of existing Valders. Both Voice/Fiber will be terminated in Union and Main next week. All 3 Voice and Data closets in S-H are sheetrocked, taped with paint to be applied mid week. We will begin Voice/Data wiring to individual jack locations on 3rd flr next week as well. The building itself is taking on a whole new look as more and more rooms and hallways are sheetrocked. The big concern at a contractors standpoint is how to ventalate building during painting.

{ Return to LIS Blog for more posts. }