Valders Update #3

Since my last update the new Valders building is progressing rapidly. The building is heated, and windows are being installed on the Ylvisaker side of the building... 3rd flr continues to be the focas, sheetrock is being hung in most every space on 3rd flr. Plumbers are working on installing critical lab ammenities. 2nd flr has some sheetrock hung. Stairways are now complete on both sides of the building and Shumacker is installing the elevator. We are going to postpone the start of Voice/Data wiring until the first week of January, this will allow for the Voice/Data closets to be tapped and painted. We are planning to pull-in the voice/fiber backbone the week of Dec 17th (subject to change) Building can be viewed via the Luther webcam www.webcam.luther.edu........